DETAIL KOLEKSI

Analisa pressure build-up pada sumur NED-1 lapangan DEY sebelum dan sesudah hydraulic fracturing


Oleh : Ivan Muhammad Akbar

Info Katalog

Nomor Panggil : 652/TP/2017

Penerbit : FTKE - Usakti

Kota Terbit : Jakarta

Tahun Terbit : 2017

Pembimbing 1 : Lestari Said

Pembimbing 2 : Onnie Ridaliani

Subyek : Transient pressure analysis;Pressure on gas reservoir

Kata Kunci : well NED-1, drilling, hydraulic fracturing.

Status Posting : Published

Status : Lengkap


File Repositori
No. Nama File Hal. Link
1. 2017_TA_TM_071.12.115_Halaman-judul.pdf 19
2. 2017_TA_TM_071.12.115_Bab-1.pdf
3. 2017_TA_TM_071.12.115_-Bab-2.pdf
4. 2017_TA_TM_071.12.115_Bab-3.pdf
5. 2017_TA_TM_071.12.115_Bab-4.pdf
6. 2017_TA_TM_071.12.115_Bab-5.pdf
7. 2017_TA_TM_071.12.115_-Daftar-Pustaka.pdf
8. 2017_TA_TM_071.12.115_Lampiran.pdf

S Sumur NED-1 merupakan sumur gas yang terletak pada lapangan DEY,Sijunjung, Sumatera Barat. Sumur ini ketika selesai dilakukan pengeboran dankomplesi, tidak mengalir sama sekali, sehingga sumur ditutup. Kemudian padatanggal 14 Oktober 2014 sumur NED-1 ini dilakukan well testing berupa pengujiandeliverabilitas dan pengujian transient tekanan berupa pressure build-up test untukmengetahui kondisi sumur.Pengujian deliverabilitas yang dilakukan menggunakan metode modifiedisochronal test, yang kemudian dianalisa menggunakan metode Rawlins. Daripengujian MIT ini, laju produksi yang tercatat ketika extended flow hanyalah 0.11MMscfd dan didapatkan nilai absolute open flow potential sebesar 0.122 MMscfd.Pada pengujian pressure build-up didapatkan permeabilitas yang sangat kecilsebesar 0.082 mD dan terdapat kerusakan berupa factor skin yang positif.Sumur NED-1 ini kemudian dilakukan stimulasi berupa hydraulicfracturing untuk mengoptimalkan produksi. Setelah dilakukannya hydraulicfracturing tersebut, dilakukan pengujian sumur lagi untuk mengetahui kondisisumur yang telah distimulasi, sehingga dapat dinilai keberhasilan dari hydraulicfracturing tersebut.Pengujian sumur setelah hydraulic fracturing ini dilakukan pada tanggal 29April 2015 berupa modified isochronal test dan pressure build-up test. Dari hasilanalisa deliverabilitas didapatkan kenaikan laju alir pada extended flow yangbernilai 4.1 MMscfd dan didapatkan nilai AOFP sebesar 4.41 MMscfd. Daripengujian PBU didapat permeabilitas 1.86 mD dan skin factor negatif.

N NED-1 well is a gas well located on DEY field, Sijunjung, West Sumatra.After drilled and perforated, this well wasn’t producing at all so then it was shut.At October 14th, 2014, well test was done in this NED-1 which was deliverabilitytest and pressure transient test using pressure build-up method, to understand thecondition of the well.The deliverability test was done using modified isochronal test and analizedusing Rawlins method. From this MIT test, the flow rate from the extended flowprogram was only 0.11 MMscfd and the absolute open flow potential was 0.122MMscfd. Pressure build-up test shows a very low permeability which was 0.082mD and detected a formation damage in form of positive skin factor.Stimulation was done on this NED-1 well using hydraulic fracturing tooptimize the production of the well. After hydraulic fracturing, well testing wasdone again on this well to know the condition of the well after stimulation andwhether the hydraulic fracturing succeeded or not.The well testing after hydraulic fracturing was done at April 29th, 2015 inform of modified isochronal test and pressure build-up test. The deliverability testshows an improvement on the well flow on the extended flow program as much as4.1 MMscfd and 4.41 MMscfd on the AOFP. From PBU test the permeability is1.86 mD and shows a negative skin factor.

Bagaimana Anda menilai Koleksi ini ?