Evaluasi penyemenan casing liner 7 pada Sumur X-1 dan Y-1 Blok LMG
P Penyemenan primer merupakan hal yang mutlak dilakukan pada setiapsumur minyak dan gas. Mengingat pentingnya kualitas penyemenan primer makaharus memenuhi standar ketentuan yang berlaku. Apabila hasil dari kualitaspenyemenan tidak baik maka semen tidak dapat menjalankan fungsinyasebagaimana mestinya. Seperti melindungi casing dari fluida korosif, menahantekanan formasi, dan sebagai media untuk jalur komunikasi antara formasi dengansumur saat diperforasi.Evaluasi penyemenan pada casing liner 7†ini menggunakan peralatanlogging yaitu Cement Bond Log (CBL) dan Segmented Bond Tool (SBT). Hasillogging CBL-SBT dianalisa meliputi pembacaan amplitude, attenuation, cementmap dan SBT wave.Dari hasil evaluasi penyemenan antara sumur X-1 dan Y-1 ditemukanperbedaan ikatan semen antara sumur X-1 dan Y-1 padahal sepanjang kedalamancasing liner 7†sumur X-1 dan Y-1 memiliki jenis formasi reservoir dan karakterreservoir yang sama serta dengan prosedur penyemenan yang sama terhadapkedua sumur tersebut seharusnya sumur X-1 dan Y-1 memiliki hasil penyemenanyang tidak jauh berbeda.Banyak faktor yang mempengaruhi kualitas dari hasil penyemenan,diantaranya: kondisi lubang bor, ketepatan dalam perhitungan bubur semen baikaditif, total fluida, dan total sak semen, serta pengalaman dari ahli penyemenan.
P Primary Cementing is an absolute necessary to do on every oil and gass wells.Given the importance of primary cementing quality standards it must meet applicableregulations. If the results of cementing quality is not good then the cement is not ableto function as it should. Such as protecting the casing from corrosive fluids, resistformation pressure, and as a mediator between the wells when the perforatedformation.Evaluation of the cementing at 7†casing liner is used logging equipment,namely Cement Bond Log (CBL) and Segmented Bond Tool (SBT). CBL-SBTlogging results are analyzed which include the reading of amplitude, attenuation,cement binder and SBT wave.From the results of the evaluation of the well cementing between the X-1 andY-1 was found differences although on every depth at 7†casing liner well X-1 and Y-1 have the same kind of reservoir formation and reservoir characteristic also, the twowells has the same exact treatment among them. The result on cementing well x-1and Y-1 should be not much of differences.There are many factors that affect the quality of the results of cementing,which is: the condition of the wellbore, the accuracy in the calculation of well cementslurry additives, the total fluid, and total bag of cement, as well as the experience ofexperts cementing.